Construction Schedule August 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 22 through August 26, 2011.

r

Post Date – August 19/11

r

Monday, August 22

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day
  • GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.

Tuesday, August 23

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day
  • GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.

Wednesday, August 24

8 The Esplanade – L Tower

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 25

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 26

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1: During the week there will be a delivery of steel piles to the site at 1 The Esplanade. An update on precise times will be posted when the information is available.
NOTE 2: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: