Construction Schedule August 22 – 26
August 19, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 22 through August 26, 2011.
r
Post Date – August 19/11
r
Monday, August 22
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day
- GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.
Tuesday, August 23
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day
- GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.
Wednesday, August 24
8 The Esplanade – L Tower
- No concrete is scheduled as of August 19.
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Thursday, August 25
8 The Esplanade – L Tower
- No concrete is scheduled as of August 19.
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Friday, August 26
8 The Esplanade – L Tower
- No concrete is scheduled as of August 19.
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.