Construction Schedule August 15 – 19

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 15 through August 19, 2011.

Post Date – August 16/11

Monday, August 15

8 The Esplanade – L Tower 

  • There will be a 45M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Tuesday, August 16

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Wednesday, August 17

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 18

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 19

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: