Construction Schedule August 15 – 19
August 16, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 15 through August 19, 2011.
Post Date – August 16/11
Monday, August 15
8 The Esplanade – L Tower
- There will be a 45M concrete pour, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Tuesday, August 16
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Wednesday, August 17
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Thursday, August 18
8 The Esplanade – L Tower
- No concrete is scheduled as of August 12.
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Friday, August 19
8 The Esplanade – L Tower
- No concrete is scheduled as of August 12.
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.