Construction Schedule August 8 – 12

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 8 through August 12, 2011.

Updated August 5, 2011

Monday, August 8

8 The Esplanade – L Tower 

  • There will be a 120M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • GFL Excavating will be drilling spoils most of the day: Dump trucks will be in and out at The Esplanade gate, just west of Scott Street.
    • There will be a significant impact on eastbound vehicular traffic.
    • There will be a significant impact on eastbound and westbound pedestrian traffic.

Tuesday, August 9

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 5 loads of concrete delivered throughout the day.
  • There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long in the afternoon. The load will come to The Esplanade gate.
    • There will be some impact on eastbound vehicular traffic.
    • There will be some significant impact on eastbound and westbound pedestrian traffic.

Wednesday, August 10

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 11

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 5.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 12

8 The Esplanade – L Tower 

  • There will be a 185M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: