Construction Schedule August 8 – 12
August 5, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 8 through August 12, 2011.
Updated August 5, 2011
Monday, August 8
8 The Esplanade – L Tower
- There will be a 120M concrete pour which may go beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- GFL Excavating will be drilling spoils most of the day: Dump trucks will be in and out at The Esplanade gate, just west of Scott Street.
- There will be a significant impact on eastbound vehicular traffic.
- There will be a significant impact on eastbound and westbound pedestrian traffic.
Tuesday, August 9
8 The Esplanade – L Tower
- There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 5 loads of concrete delivered throughout the day.
- There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long in the afternoon. The load will come to The Esplanade gate.
- There will be some impact on eastbound vehicular traffic.
- There will be some significant impact on eastbound and westbound pedestrian traffic.
Wednesday, August 10
8 The Esplanade – L Tower
- There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Thursday, August 11
8 The Esplanade – L Tower
- No concrete is scheduled as of August 5.
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Friday, August 12
8 The Esplanade – L Tower
- There will be a 185M concrete pour which may go beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.