Construction Schedule – August 2 – 6
August 2, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 2 through August 6, 2011.
Updated August 2, 2011
t
Tuesday, August 2
8 The Esplanade – L Tower
- There will be a 180M concrete pour which may go beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- Concrete truck deliveries are scheduled throughout the day.
Wednesday, August 3
8 The Esplanade – L Tower
- There will be a 72M concrete pour which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- Concrete truck deliveries are scheduled throughout the day.
- There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long. The load will come to The Esplanade gate.
- Because it is an oversized load the truck delivering it will leave Deep Foundation’s yard at approximately 9:00 am under police escort and make its way to the site via Jarvis St, west across The Esplanade toward Yonge Street.
- Unfortunately, during delivery there will be a significant impact on vehicular and pedestrian traffic in the vicinity of 1 The Esplanade. This is expected to occur between approximately 10 am and 11 am.
Thursday, August 4
8 The Esplanade – L Tower
- There will be a 72M concrete pour which is not expected to beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- Concrete truck deliveries are scheduled throughout the day.
Friday, August 5
8 The Esplanade – L Tower
- There will be a 108M concrete pour which may go beyond 7:00 pm
- Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- Concrete truck deliveries are scheduled throughout the day.
Saturday, August 6
8 The Esplanade – L Tower
- There will be a Dominus labour crew in for housekeeping activities on the site between 9:00 am and 1:00 pm