Updated: Construction Schedule August 29 – September 2

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 29 through September 2, 2011.

UPDATED: 30 August 2011

Monday, August 29

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 26.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

 Tuesday, August 30

8 The Esplanade – L Tower 

  • There will be a 140M concrete pour beginning at 9AM

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, August 31

8 The Esplanade – L Tower

  • There will be a steel delivery at 7:00am and 86M Concrete pour starting at 1:00pm which is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage  (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.
  • Update: Deep Foundations has an 85 foot long load of steel piles being delivered under police escort at 1:00 pm. The load will come down The Esplanade.

Thursday, September 1

8 The Esplanade – L Tower 

  • There will be a 86M concrete pour starting at 1:00pm which not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • Update: GFL Excavating will be on site removing drilling spoils. There will be 4 dump trucks doing 4 rounds each for a total of 16 loads.

Friday, September 2

8 The Esplanade – L Tower 

  • There will be a 86M concrete pour starting at 1:00pm which not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1:  Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday.

Caisson Drilling at 1 The Esplanade

Drilling at 1 The Esplanade

image

Drill at work on The Embankment - 1 The Esplanade

image

Steel piles wating to be placed into the caissons

image

Steel and drill. 1 The Esplanade.

image

Casisson drilling.

image

Crane & Sky. 25 The Esplanade in the background.

image

Drill at 1 The Esplanade seen from Platform 1 Union Station.

Active construction photographs at 1 The Esplanade, site of the Backstage Condominium and the L Tower’s underground parking, from the week of August 22.

Construction on The Esplanade week of August 22 – 26.

Scenes from the construction of the L Tower and Backstage condominiums – August 22 – 26, 2011.

image

image

image

image

image

image

image

Construction Schedule August 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 22 through August 26, 2011.

r

Post Date – August 19/11

r

Monday, August 22

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day
  • GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.

Tuesday, August 23

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day
  • GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.

Wednesday, August 24

8 The Esplanade – L Tower

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 25

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 26

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1: During the week there will be a delivery of steel piles to the site at 1 The Esplanade. An update on precise times will be posted when the information is available.
NOTE 2: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

L Tower Construction Update

L Tower Construction update as of August 17, 2011.

Thursday, August 18

L Tower – 8 The Esplanade

There will be a 45M concrete pour that is not expected to go beyond 7:00 pm.

Friday, August 19

L Tower – 8 The Esplanade

There will be a 45M concrete pour that is not expected to go beyond 7:00 pm.

Construction Schedule August 15 – 19

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 15 through August 19, 2011.

Post Date – August 16/11

Monday, August 15

8 The Esplanade – L Tower 

  • There will be a 45M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Tuesday, August 16

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Wednesday, August 17

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 18

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 19

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Construction Schedule August 8 – 12

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 8 through August 12, 2011.

Updated August 5, 2011

Monday, August 8

8 The Esplanade – L Tower 

  • There will be a 120M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • GFL Excavating will be drilling spoils most of the day: Dump trucks will be in and out at The Esplanade gate, just west of Scott Street.
    • There will be a significant impact on eastbound vehicular traffic.
    • There will be a significant impact on eastbound and westbound pedestrian traffic.

Tuesday, August 9

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 5 loads of concrete delivered throughout the day.
  • There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long in the afternoon. The load will come to The Esplanade gate.
    • There will be some impact on eastbound vehicular traffic.
    • There will be some significant impact on eastbound and westbound pedestrian traffic.

Wednesday, August 10

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 11

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 5.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 12

8 The Esplanade – L Tower 

  • There will be a 185M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Construction scenes on a cloudy summer day: 8-3-11

The Esplanade looking west to Yonge Street, concrete bucket in the backround, August 3, 2011

Working on the embankment at 1 The Esplanade - August 3, 2011

Crane work at 1 The Esplanade, August 3, 2011

Drilling caissons at 1 The Esplanade, August 3 2011

 

The Esplanade looking east from Yonge - August 3, 2011

 

 

Construction Schedule – August 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 2 through August 6, 2011.

Updated August 2, 2011

t

Tuesday, August 2

8 The Esplanade – L Tower 

  • There will be a 180M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.

Wednesday, August 3

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.
  • There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long. The load will come to The Esplanade gate.
    • Because it is an oversized load the truck delivering it will leave Deep Foundation’s yard at approximately 9:00 am under police escort and make its way to the site via Jarvis St, west across The Esplanade toward Yonge Street.
    • Unfortunately, during delivery there will be a significant impact on vehicular and pedestrian traffic in the vicinity of 1 The Esplanade. This is expected to occur between approximately 10 am and 11 am.

Thursday, August 4

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.

Friday, August 5

8 The Esplanade – L Tower 

  • There will be a 108M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.

Saturday, August 6

8 The Esplanade – L Tower 

  • There will be a Dominus labour crew in for housekeeping activities on the site between 9:00 am and 1:00 pm

 

NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.