Construction Schedule July 25 – 30 – Updated July 29

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of July 25 through July 30, 2011. [Updated July 29.]

t

Monday, July 25

8 The Esplanade – L Tower 

  • There will be a 36M concrete pour which is not expected to go beyond 7:00 pm
  • Several material and supply deliveries will occur between 7:00 am – 4:00 pm

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • There are eight (8) concrete truck deliveries scheduled.

Tuesday, July 26

8 The Esplanade – L Tower 

  • There will be a 7:00 am rebar (steel) delivery to the site.
  • There is no concrete pour scheduled as of the posting date, July 24.
  • Several material and supply deliveries will occur between 7:00 am – 4:00 pm

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • There are eight (8) concrete truck deliveries scheduled.

Wednesday, July 27

8 The Esplanade – L Tower 

  • There will be a 7:00 am rebar (steel) delivery to the site.
  • There is no concrete pour scheduled as of the posting date, July 24.
  • Several material and supply deliveries will occur between 7:00 am – 4:00 pm

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • There are eight (8) concrete truck deliveries scheduled.
  • There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long. The load will come to The Esplanade gate.
    • Because it is an oversized load the truck delivering it will leave Deep Foundation’s yard at 9:00 am under police escort and make its way to the site via Jarvis St, west across The Esplanade toward Yonge Street.
    • Unfortunately, during delivery there will be a significant impact on vehicular and pedestrian traffic in the vicinity of 1 The Esplanade. This is expected to occur between approximately 10 am and 11 am.

Thursday, July 28

8 The Esplanade – L Tower 

  • The concrete pour scheduled for today has been cancelled.
  • Several material and supply deliveries will occur between 7:00 am – 4:00 pm

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • There are eight (8) concrete truck deliveries scheduled.

Friday, July 29

8 The Esplanade – L Tower 

  • CANCELLED There will NOT be a 180M concrete pour which may go beyond 7:00 pm (as of 7/29/11) – Rescheduled to Tuesday August 2.
  • Several material and supply deliveries will occur between 7:00 am – 4:00 pm

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • There are eight (8) concrete truck deliveries scheduled.

Saturday, July 30

8 The Esplanade – L Tower 

  • There will be a Dominus labour crew in for housekeeping activities on the site between 9:00 am and 1:00 pm

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: