1 The Esplanade Construction Schedule: July 18 – 22.
July 16, 2011 Leave a comment
Scheduled construction activity for 1 The Esplanade–L Tower parking garage and Backstage condo–July 18 through July 22.
Monday, July 18
Sub-contractor, Deep Foundation has 4 semi-trailer truck deliveries at The Esplanade gate. During these deliveries there will be a significant impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.
Tuesday, July 19
Sub-contractor, Deep Foundation will be starting caisson wall drilling. There will be up to six concrete deliveries into the site at The Esplanade gate. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.
Wednesday, July 20
Sub-contractor, Deep Foundation will be drilling the caisson wall. There will be up to six concrete deliveries into the site at The Esplanade gate. Deep Foundation will also be delivering one load of steel pile on a semi-trailer truck. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.
Thursday, July 21
Sub-contractor, Deep Foundation will be drilling the caisson wall. There will be up to six concrete deliveries into the site at The Esplanade gate. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.
Friday July 22
Sub-contractor, Deep Foundation will be drilling the caisson wall. There will be up to six concrete deliveries into the site at The Esplanade gate. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.