L Tower Construction Schedule July 16 – 22

8 The Esplanade – L Tower Construction Schedule July 16 – 22

Saturday, July 16

Sub-contractor, Premform will loosen form bolts and do housekeeping on site from 9:00 am to 3:00 pm.

No crane work is scheduled.

Monday, July 18

No concrete pours are scheduled.

Tuesday, July 19

There will be a 36M concrete pour starting at 1:00 pm, which is not expected to go beyond 7:00 pm. 

Wednesday, July 20

There will be a 36M concrete pour starting at 1:00 pm, which is not expected to go beyond 7:00 pm. 

Thursday, July 21

No concrete pours are scheduled at the time of posting (July 15).

Friday, July 22

No concrete pours are scheduled at the time of posting (July 15).

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: