Construction Schedule July 11 – 15

Outline of planned construction schedule for the week of July 11th through July 18th

Monday, July 11

8 The Esplanade – L Tower

  • A 45M concrete pour not expected to go beyond 7:00 pm.

1 The Esplanade – L Tower Parking & Backstage foundation

  • Sub-contractor, GFL Excavating will be running one dump truck all day building a ramp, entering and exiting through The Esplanade gate.
  • Sub-contractor, Deep Foundation has one concrete truck for guide wall. Access at the Esplanade gate.

Tuesday, July 12

8 The Esplanade – L Tower

  • 45M concrete pour not expected to go beyond 7:00 pm.

1 The Esplanade – L Tower Parking & Backstage foundation

  • Sub-contractor, Deep Foundation will have 2 tractor-trailer loads delivering drill rig components. The construction management team is seeking to use Market Street access for this.

Wednesday, July 13

8 The Esplanade – L Tower

  • 45M concrete pour not expected to go beyond 7:00 pm.

1 The Esplanade – L Tower Parking & Backstage foundation

  • Sub-contractor, Deep Foundation will have 2 semi tractor trailers delivering pile steel and one float delivering the drip rig. The construction management team is seeking to use Market Street access for this.

Thursday, July 14

8 The Esplanade – L Tower

  • No concrete pour scheduled as of today.

1 The Esplanade – L Tower Parking & Backstage foundation

  • Sub-contractor, Deep Foundation will be drilling caissons. Three concrete trucks will be accessing the site via The Esplanade gate.

Friday, July 15

8 The Esplanade – L Tower

  • No concrete pour scheduled as of today.

1 The Esplanade – L Tower Parking & Backstage foundation

  • Sub-contractor, Deep Foundation will be drilling caissons. Three concrete trucks will be accessing the site via The Esplanade gate.

Please note: that while there will be some unavoidable short-term delays for vehicular and pedestrian traffic along The Esplanade from Scott Street west to Yonge Street, no temporary street closure permit applications are planned for this week.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: