July 4 – 8 Construction Outline
July 4, 2011 Leave a comment
At 8 The Esplanade – L Tower
Monday, July 4 – 36M concrete pour not expected to go beyond 7:00 pm.
Tuesday, July 5 – UPDATED: There will be no concrete pour on Tuesday.
Wednesday, July 6 – A single lane Temporary Street Occupation application for Yonge Street has been re-submitted to the City of Toronto to facilitate a 200M+ concrete to pour utilizing a concrete pump. If City of Toronto Transportation Services deem this lane occupation to be necessary to ensure the safe operation of the planned 200M+ concrete pour, it will go forward and copies of the permit will be distributed adjacent businesses and residential buildings.
PLEASE NOTE: The July 6 concrete pour is now not expected to go past 7:00 pm.
Thursday, July 7 – 81M+ concrete pour not expected to go beyond 7:00 pm.
Friday, July 8 – 54M+ concrete pour not expected to go beyond 7:00 pm.
At 1 The Esplanade – L Tower parking garage/Backstage foundation:
Monday, July 4 – pouring guide wall. Concrete at 11;00 am and 1:00 pm.
Tuesday, July 5 – pouring guide wall. Concrete at 11:00 am and 1:00 pm,
Wednesday, July 6 – pouring guide wall. Concrete at 11:00 am and 1:00 pm.
Thursday, July 7 – pouring guide wall. Concrete at 11:00 am and 1:00 pm.
Friday, July 8 – pouring guide wall. Concrete at 11:00 am and 1:00 pm.
NOTE: There may be a steel pile delivery during the week but it has not been confirmed by the construction team.