At 8 The Esplanade – L Tower

Monday, July 4 – 36M concrete pour not expected to go beyond 7:00 pm.

Tuesday, July 5 – UPDATED: There will be no concrete pour on Tuesday.

Wednesday, July 6 – A single lane Temporary Street Occupation application for Yonge Street has been re-submitted to the City of Toronto to facilitate a 200M+ concrete to pour utilizing a concrete pump. If City of Toronto Transportation Services deem this lane occupation to be necessary to ensure the safe operation of the planned 200M+ concrete pour, it will go forward and copies of the permit will be distributed adjacent businesses and residential buildings.

PLEASE NOTE: The July 6 concrete pour is now not expected to go past 7:00 pm.

Thursday, July 7 – 81M+ concrete pour not expected to go beyond 7:00 pm.

Friday, July 8 – 54M+ concrete pour not expected to go beyond 7:00 pm.

At 1 The Esplanade – L Tower parking garage/Backstage foundation:

Monday, July 4 – pouring guide wall. Concrete at 11;00 am and 1:00 pm.

Tuesday, July 5 – pouring guide wall. Concrete at 11:00 am and 1:00 pm,

Wednesday, July 6 – pouring guide wall. Concrete at 11:00 am and 1:00 pm.

Thursday, July 7 – pouring guide wall. Concrete at 11:00 am and 1:00 pm.

Friday, July 8 – pouring guide wall. Concrete at 11:00 am and 1:00 pm.

NOTE: There may be a steel pile delivery during the week but it has not been confirmed by the construction team.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: