Construction Schedule July 25 – 30 – Updated July 29
July 29, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of July 25 through July 30, 2011. [Updated July 29.]
t
Monday, July 25
8 The Esplanade – L Tower
- There will be a 36M concrete pour which is not expected to go beyond 7:00 pm
- Several material and supply deliveries will occur between 7:00 am – 4:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- There are eight (8) concrete truck deliveries scheduled.
Tuesday, July 26
8 The Esplanade – L Tower
- There will be a 7:00 am rebar (steel) delivery to the site.
- There is no concrete pour scheduled as of the posting date, July 24.
- Several material and supply deliveries will occur between 7:00 am – 4:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- There are eight (8) concrete truck deliveries scheduled.
Wednesday, July 27
8 The Esplanade – L Tower
- There will be a 7:00 am rebar (steel) delivery to the site.
- There is no concrete pour scheduled as of the posting date, July 24.
- Several material and supply deliveries will occur between 7:00 am – 4:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- There are eight (8) concrete truck deliveries scheduled.
- There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long. The load will come to The Esplanade gate.
- Because it is an oversized load the truck delivering it will leave Deep Foundation’s yard at 9:00 am under police escort and make its way to the site via Jarvis St, west across The Esplanade toward Yonge Street.
- Unfortunately, during delivery there will be a significant impact on vehicular and pedestrian traffic in the vicinity of 1 The Esplanade. This is expected to occur between approximately 10 am and 11 am.
Thursday, July 28
8 The Esplanade – L Tower
- The concrete pour scheduled for today has been cancelled.
- Several material and supply deliveries will occur between 7:00 am – 4:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- There are eight (8) concrete truck deliveries scheduled.
Friday, July 29
8 The Esplanade – L Tower
- CANCELLED There will NOT be a 180M concrete pour which may go beyond 7:00 pm (as of 7/29/11) – Rescheduled to Tuesday August 2.
- Several material and supply deliveries will occur between 7:00 am – 4:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons.
- There are eight (8) concrete truck deliveries scheduled.
Saturday, July 30
8 The Esplanade – L Tower
- There will be a Dominus labour crew in for housekeeping activities on the site between 9:00 am and 1:00 pm