June 27 – 30 Construction Highlights

w

L Tower – 8 The Esplanade – Concrete Pour

w

Tuesday June 28 – The construction team will be using a concrete pump to pour walls and columns.

Wednesday June 29 – The construction team will be using a concrete pump to pour walls and columns.

NOTE: Work on this may go past 7 pm in order to complete these pours.
w

1 The Esplanade – Guide Wall Material Delivery & Pour

w
Monday June 27 – delivery of construction material and equipment to the site, with access from Market Street.

Tuesday June 28 – delivering construction material and equipment to the sit, with access from Market Street.

Wednesday June 29 – concrete trucks to pour guide wall, with access from Market Street.

Thursday June 30 – concrete trucks to pour guide wall, with access from Market Street.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: