Re-installing hoarding at 1 The Esplanade

This week, June 13 – 17, work is progressing on re-installing the hoarding on the embankment at 1 The Esplanade. Once complete, guide wall work is scheduled to begin the of June 20th. Drilling for caisson installation is scheduled to begin the following week, June 27th, in preparation for the initial work to construct the L Tower’s underground parking. More details on this work will be posted later this week.

This photograph of the hoarding work was provided by the Dominus Construction team