June 27 – 30 Construction Highlights

w

L Tower – 8 The Esplanade – Concrete Pour

w

Tuesday June 28 – The construction team will be using a concrete pump to pour walls and columns.

Wednesday June 29 – The construction team will be using a concrete pump to pour walls and columns.

NOTE: Work on this may go past 7 pm in order to complete these pours.
w

1 The Esplanade – Guide Wall Material Delivery & Pour

w
Monday June 27 – delivery of construction material and equipment to the site, with access from Market Street.

Tuesday June 28 – delivering construction material and equipment to the sit, with access from Market Street.

Wednesday June 29 – concrete trucks to pour guide wall, with access from Market Street.

Thursday June 30 – concrete trucks to pour guide wall, with access from Market Street.

June 27 – 30 – Temporary Street Occupation

This coming week —  Monday, June 27 through Thursday, June 30 the Dominus construction team will continue the installation of a self climbing form-work protection system and conduct related work on the L Tower, 8 The Esplanade.

Due to the amount and size of the materials that need to be hoisted over the roadway, construction management has again applied for and received a Temporary Street Occupation Permit from the City of Toronto, Transportation Services — Permit Number 53972402– to occupy the eastbound lane of The Esplanade between Yonge Street and Scott Street.

The time period covered by this permit is as follows:

  • Monday, June 27 9:30 am to 6:00 pm
  • Tuesday, June 28 from 9:30 am to 6:00 pm
  • Wednesday, June 29 from 9:30 am to 6:00 pm
  • Thursday, June 30 from 9:30 am to 6:00 pm

NOTE: One Paid Duty Officer is required for vehicular and pedestrian traffic control.

To view the permit please click on the link below:

Temporary Street Occupation Permit – City of Toronto, Transportation Services — Permit Number 53972402

Concrete Pours daily for June 21 – 24

There will be concrete pours daily the balance of this week for the L Tower, Tuesday June 21 through Friday, June 24.

At the time of this post — 5 pm, June 20 — it is not anticipated that these pours will require work to go past 7 pm. We will be updating this information daily. Please check back for further updates.

Monday, June 20 – Concrete Pour

A concrete pour is scheduled for Monday, June 20.

Please note: This pour may require work to continue past 7:00 pm

Please click on this link for more information on concrete pours.

June 20 – June 24 – Temporary Street Occupation for Hoisting

Staring Monday June 20 through Friday June 24 construction team will be installing a self climbing form-work protection system to provide greater safety to our construction workers on site along with additional safety for pedestrians passing below.

Due to the amount of material, installation time and large materials needed to be hoisted over the roadway, a Temporary Street Occupation Permit has been received from the City of Toronto — Permit Number 53972401 — to occupy the eastbound lane of The Esplanade between Yonge Street and Scott Street.

The time period covered by this permit is as follows:

Monday, June 20, from 9:30 am to 6:00 pm

Tuesday, June 21 from 9:30 am to 6:00 pm

Wednesday, June 22 from 9:30 am to 6:00 pm

Thursday, June 23 from 9:30 am to 6:00 pm

Friday, June 24 from 9:30 am to 6:00 pm

NOTE: One Paid Duty Officer is required for vehicular and pedestrian traffic control.

Please click here to view a copy of the permit: SLTOWER con11061716330

Schedule for Thursday June 16 + Friday June 17

Thursday, June 16

An L Tower level 6 slab 120M concrete pour is scheduled to commence at 1100 am. This pour will continue past 7:00 pm.

Friday, June 17

The continuation of the L Tower level 6 slab 120M concrete pour is scheduled to commence at 9:00 am. Please note that this pour may stretch beyond 7:00 pm.

 


 

Re-installing hoarding at 1 The Esplanade

This week, June 13 – 17, work is progressing on re-installing the hoarding on the embankment at 1 The Esplanade. Once complete, guide wall work is scheduled to begin the of June 20th. Drilling for caisson installation is scheduled to begin the following week, June 27th, in preparation for the initial work to construct the L Tower’s underground parking. More details on this work will be posted later this week.

This photograph of the hoarding work was provided by the Dominus Construction team

Construction Schedule June 13 – 17

Construction schedule outlook for the week of June 13 – 17

Monday, June 13

The construction team has scheduled a pour of 55+m for columns and walls, it is scheduled to begin at 1 pm and may stretch beyond 7 pm.

Tuesday, June 14

A 36M wall and column concrete pour is now scheduled to commence at 1:00 pm. Please note that this pour may stretch beyond 7:00 pm.

Wednesday, June 15

A 36M wall and column concrete pour is now scheduled to commence at 1:00 pm. Please note that this pour may stretch beyond 7:00 pm.

Thursday, June 16

An L Tower level 6 slab 120M concrete pour is scheduled to commence at 1100 am. This pour will continue past 7:00 pm.

Friday, June 17

The continuation of the L Tower level 6 slab 120M concrete pour is scheduled to commence at 9:00 am. Please note that this pour may stretch beyond 7:00 pm.

A note on Concrete Pours:

In relation to any concrete pour, after the trucks that have delivered the concrete leave, the construction crews must finish the freshly poured slab.  This process involves the concrete finishers waiting until the concrete hardens enough (1-3 hours sometimes more, depending on ambient temperature) to allow the finishing machines on top of the slab to provide a smooth level concrete surface.  If this were not done the concrete would harden creating a deficient structural component, jeopardizing the integrity of tower construction.

Timing of Concrete Pours:

Prior to any concrete pour the required forming and rebar work must be completed. This frequently takes several hours. As well, the timing of concrete pours are dependant on the concrete suppliers availability to deliver concrete to the site.

In a large pour, for example for a floor slab, even if it is possible to begin in the morning, the work may still stretch into the evening, given the amount of concrete and the time it takes to pour and finish it. 

Every effort is made to have work stay within the prescribed times in the City of Toronto’s construction noise by-law. However the by-law clearly permits concrete pouring to continue past 7:00 pm when construction logistics require this. 

Friday June 10 – Concrete Pour

Friday June 10 Notice

As noted in yesterday’s post, today Friday, June 10, the construction team has scheduled 36M+ of concrete to start at 12:30 pm and continue until complete.

 

June 9 2011 – Update

June 9 Afternoon Update

The L Tower construction crew will now be pouring 90M of  concrete this afternoon commencing shortly after 1:30 pm. It is anticipated that this will necessitate working past 7:00 pm.

This is a vertical pour, including a section of the elevator core.

Friday June 10 Notice

For Friday, June 10, the construction team has scheduled 36M+ of concrete to start at 12:30 pm.

Revisions for Next Week: [Please see updated information as of  June 10 at https://ltowerconstructioninfo.com/2011/06/10/construciton-outlook-june-13-15/]

As of today, June 9, the work schedule has been revised and the anticipated concrete pour Monday June 13 has been rescheduled for Wednesday June 15.

As of today’s construction update there are no concrete pours scheduled for Monday and Tuesday of next week.

Wednesday June 15 Notice

The L Tower  Level 6 slab is now scheduled to be poured one Wednesday June 15 and it is anticipated working will go past 7:00 pm.

A note on concrete pours:

In relation to any concrete pour, after the trucks that have delivered the concrete leave, the construction crews must finish the freshly poured slab.  This process involves the concrete finishers waiting until the concrete hardens enough (1-3 hours sometimes more, depending on ambient temperature) to allow the finishing machines on top of the slab to provide a smooth level concrete surface.  If this were not done the concrete would harden creating a deficient structural component, jeopardizing the integrity of tower construction.

%d bloggers like this: