Recap on Dec 5 Long Reach Back-hoe delivery

UPDATE: The Long Reach Back-hoe that was scheduled to arrive Wednesday, December 5, under police escort between 6:20 am and 7:00 am. It actually arrived at 5:30 am as the City of Toronto permit stipulated that the semi-trailer float (truck) had to be out of the downtown core prior to 6:00 am. Unfortunately we did not receive accurate information on the timing of the delivery.

On December 4 we were advised by subcontractor GFL Excavating that the back-hoe was coming early in the morning, instead of the originally and preferred plan to deliver it at midday. GFL could not get a permit for midday because City of Toronto staff considered the impact on daytime traffic would be too onerous. The permit was issued for 5 am to 6 am delivery and GFL was instructed by the City and the Police to have their large delivery truck off the site an out of the downtown by 6:00 am.

In this case the regulations for large deliveries trumped the regulations for construction noise; the regulating bodies determined that the traffic regulations trumped the standard construction noise regulations.  

Please click here for a revised Backstage – 1 The Esplanade construction schedule.

 
Please click here for a revised Backstage – 1 The Esplanade construction schedule.

L Tower Construction Schedule June 18 – 22

This is the current construction schedule for 8 The Esplanade – L Tower – for   June 18 – 22, 2012

Posted June 15, 2012

NOTE:

  • The L Tower is scheduled to reach 46 floors this week.

Monday, June 18

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Tuesday, June 19

  • A 220M (cubic metre) slab concrete pour, at level 46, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Wednesday, June 20

  • A 122M (cubic metre) part 1, wall and column concrete pour, levels 46 – 47, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Thursday, June 21

  • A 70M (cubic metre) part 2, wall and column concrete pour, levels 46 – 47, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Friday, June 22

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 18 – 22 summary highlights: L Tower & Backstage Construction June 18-22

L Tower Construction Schedule June 11 – 15

This is the current construction schedule for 8 The Esplanade – L Tower – for   June 11 – 15, 2012

Posted June 8, 2012

NOTE:

  • The L Tower is scheduled to reach 45 floors this week.

Monday, June 11

  • A 101M (cubic metre) part 2, wall and column concrete pour, levels 44 – 45, starting at 1 pm, which is not expected to extend beyond 7:00 pm.
  • The hoist will be climbed (raised) three floors. 

Tuesday, June 12

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Wednesday, June 13

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open
  • A 220M (cubic metre) slab concrete pour, at level 45, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, June 14

  • A 101M (cubic metre) part 1, wall and column concrete pour, levels 45 – 46, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Friday, June 15

  • A 101M (cubic metre) part 2, wall and column concrete pour, levels 45 – 46, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15

L Tower Concrete & Rebar, June 5, 2012

Concrete truck backing into the site at the L Tower, June 5, 2012

 

Concrete truck at the L Tower, June 5, 2012

 

Rebar delivery at the L Tower, June 5, 2012

 

Rebar delivery at the L Tower, looking east from Yonge Street, June 5, 2012

L Tower Construction Schedule May 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  22 – 26, 2012

Posted May 18, 2012

Note: The L Tower is scheduled to reach 42 floors this week.

Monday, May 21 – Victoria Day Holiday 

Tuesday, May 22

  • Heat Pump delivery starting at 7:30 am, with the estimated completion of the delivery at 11:00 am. 
    • Please note there may be some short-term disruptions to eastbound vehicular traffic.
    • Pedestrian traffic will remain open.
  • A 92M (part 1) wall and column concrete pour, levels 41 – 42 starting at Noon, which is not expected to extend beyond 7:00 pm.

Wednesday, May 23

  • A 96M (part 2) wall and column concrete pour, levels 41 – 42 starting at Noon, which is not expected to extend beyond 7:00 pm.

Thursday, May 24

Friday, May 25

  • A 215M slab concrete pour, level 42, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Saturday, May 26

  • Hoist maintenance will commence at 9:00 am and the estimated completion time for this work is 1:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 22 – 26 summary highlights: L Tower & Backstage Construction May 22 – 26

L Tower Construction Schedule April 23 – 27

This is the current construction schedule for 8 The Esplanade – L Tower for April 23 – 27, 2012

Posted April 20, 2012

Note: The L Tower is scheduled to reach 38 floors this week.

Monday, April 23

  • Window delivery starting at 7:00 am.
  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 37, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, April 24

  • Window delivery starting at 7:00 am.
  • A 99M (part 1) wall and column concrete pour, levels 37 – 38 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, April 25

  • Rebar delivery starting at 12:30 pm. 
  • A 108M (part 2) wall and column concrete pour, levels 36 – 37, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, April 26

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, April 27

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights:  L Tower & Backstage Construction April 23-27

L Tower Construction Schedule April 9 – 13

This is the current construction schedule for 8 The Esplanade – L Tower for April 9 – 12, 2012

Posted April 7, 2012

Note: The L Tower is scheduled to reach 35 floors this week.

Monday, April 9

  • Heat Pump (for individual condo suites) delivery starting at 7:30 am.
  • A 108M (part 2) wall and column concrete pour, levels 34 – 35, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, April 10

  • Rebar delivery starting at 7:00 am.
  • Window delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm

Wednesday, April 11

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 35, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, April 12

  • A 99M (part 1) wall and column concrete pour, levels 35 – 36 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

  Friday, April 13

  • Rebar delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 35 – 36, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 9 – 13 summary update: 1+8 The Esplanade – Construction Notice-April-9-13

L Tower Construction Schedule April 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower for April 2 – 6, 2012

Posted March 30, 2012

Note: The L Tower is scheduled to reach 34 floors this week.

Monday, April 2

  • A 108M (part 2) wall and column concrete pour, levels 33 – 34, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • Rebar delivery starting at 12:30 pm

Tuesday, April 3

  • Rebar delivery starting at 12:30 pm

Wednesday, April 4

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 34, starting 10:00 am, which is not expected to extend beyond 7:00 pm.
  • Rebar delivery starting at 12:30 pm.

Thursday, April 5

  • Heat Pump (for individual condo suites) delivery starting at 7:30 am.
  • A 99M (part 1) wall and column concrete pour, levels 34 – 35, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Good Friday – Holiday – April 6

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

L Tower Construction Schedule March 12 – 17

This is the current construction schedule for 8 The Esplanade – L Tower for March 12 – 17, 2012

Posted March 9, 2012

Monday, March 12

  • Steel delivery at 7:00 am.
  • Steel delivery at Noon.

Tuesday, March 13

  • Steel delivery at 10:00 am.
  • A 200M concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Wednesday, March 14

  • A 90M concrete pour scheduled to start at 2:00 pm, which may extend beyond 7:00 pm.

Thursday, March 15

  • Steel delivery at Noon
  • A 100M concrete pour scheduled to start at 1:00 pm, which may extend beyond 7:00 pm.

Friday, March 16

  • Steel delivery at 7:00 am.
  • Steel delivery at Noon.

Saturday, March 17

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 12 – 17 inclusive: 1+8 The Esplanade – Construction Notice-March-12-17

L Tower at 23 floors and counting

Photos from January 9, 2012 of the Daniel Libeskind designed L Tower, from Castlepoint, Cityzen and Fernbrook Homes located at 8 The Esplanade – 23 floors and counting:

L Tower looking west from The Esplanade, 1/9/12

 

L Tower at 23 floors, 1/9/12

 

L Tower looking up & NE, 23 stories and rising, 1/9/12

 

L Tower looking east from Platform 1, Union Station Train Shed, 1/9/12

Follow

Get every new post delivered to your Inbox.

Join 63 other followers

%d bloggers like this: