Backstage Construction Schedule – April 9 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 9 – 13, 2012

Updated April 10, 2012

NOTE: Subcontractor, Deep Foundation will be delivering a large drill rig to the site at 1 The Esplanade in order to complete the piles and caisson work this week. The delivery date is not confirmed at the time of posting. Please check back for updated information.

Monday, April 9

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 10

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 11

  • Subcontractor, Deep Foundation, will be delivering a drill rig to the site at 1 The Esplanade after 9 am, under police escort.
    • There will be short-term disruptions to vehicular and pedestrian traffic. The construction management team apologizes for any short-term inconvenience this may cause.
  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 12

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Friday,  April 13

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 9 – 13 summary update: 1+8 The Esplanade – Construction Notice-April-9-13

Backstage Construction Schedule – April 2 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 2 – 6, 2012

Posted March 30, 2012

Monday, April 2

  • Sub-contractor, Deep Foundation, will be floating in the tie back machine in the morning.
  • NOTE: This will unfortunately cause short-term delays for vehicular and pedestrian traffic.

Tuesday, April 3

  • Sub-contractor, Deep Foundation, will be installing tie backs.

Wednesday, April 4

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Thursday, April 5

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Good Friday – Holiday – April 6

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

1 The Esplanade – Construction Schedule December 19 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 19 – 23, 2011

Posted December 16, 2011

Monday, December 19

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Tuesday, December 20

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Wednesday, December 21

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Thursday, December 22

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Friday, December 23

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Saturday, December 24

Happy Holidays!

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule November 28 – December 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 28 – December 2, 2011

Posted November 25, 2011

Monday, November 28

  • Sub-contractor Deep Foundation will be installing tie backs.

Tuesday, November 29

  • Sub-contractor Deep Foundation will be installing tie backs.

Wedensday, November 30

  • Sub-contractor Deep Foundation will be installing tie backs.

Thursday, December 1

  • Sub-contractor Deep Foundation will be installing tie backs.

Friday, December 2

  • Sub-contractor Deep Foundation will be installing tie backs.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Follow

Get every new post delivered to your Inbox.

Join 37 other followers