Esplanade re-opened between Scott & Yonge

February 28, 2013  5:00 pm

The ice has stopped falling from the forming, crane and building edge at the L Tower.

The roadway has been re-opened.

Security staff will keep an eye on the situation. All the same please exercise caution traversing the roadway on The Esplanade between Scott Street and Yonge Street. 

Many thanks for your patience and understanding.

Esplanade Road Closure Update: Open Sept 20. Closed Sept 21 and 24

The Esplanade between Scott Street and Yonge Street was open today, September 19 and will be open tomorrow September 20. It will be closed again on Friday, September 21 and Monday September 24.

The cause of this change as noted in a previous post (here), were the transportation and wide-load delivery challenges for the steel lining that was to be installed, starting on Tuesday, September 18. Initial preparations were done on Tuesday with the mobile crane. However, without the steel lining no further work could be done.

Mobile Crane on The Esplanade, September 18/12

This delay and rescheduling has been caused by factors beyond the control of the construction management team. They apologize again for the inconvenience these changes may cause.


The revised plan will not exceed the original number of permitted road closure days and stays within the permitted hours – 7 am – 6 am.

UPDATE as of September 19, 2012

Road Closure: The Esplanade between Scott Street and Yonge Street:

  • Thursday, September 20 – OPEN
  • Friday, September 21, CLOSED 7 am – 6 pm
  • Monday, September 24, CLOSED 7 am – 6 pm

Wide-load Deliveries under police escort 

  • Friday, September 21 – after 10 am.
  • Monday, September 25 – after 10 am

    Please click on this link for a downloadable PDF version of this post: Esplanade Road Closure Update

Wide-load steel deliveries to Backstage Sept 18 – 21

Wide-Load CANCELLED due to traffic and transportation issues – Please note that there will be wide-load steel deliveries under police escort to the Backstage construction site each morning from September 18 – 21 — We will update information regarding September 19 -21 as soon as it becomes available. 

  • These deliveries will be made to the site at 1 The Esplanade, via Scott Street, during the daily — September 18 – 21, 7 am to 6 pm — road closure period.
  • We expect the loads will arrive between 7 am and 10 am depending on traffic and road conditions.
  • We will update this information if there are changes to the delivery schedule or as new information becomes available.

The construction  management team apologizes for any inconvenience. All efforts will be made to ensure that this work is carried out as efficiently as possible. 

Tunnel boring equipment loading on The Esplanade.

image

July 23, 2012 The Esplanade Road has been closed between Scott Street and Yonge Street since July 16 to permit the safe construction of and underground tunnel between the L Tower’s parking, located beneath the site of the Backstage condo, and the L Tower itself. Prepatory work to dig out the opening for the tunnel boring machine was conducted last week. Today, equipment to support the tunnel boring machine is being brought into place.

Backstage Construction Schedule – April 23 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 23 – 27, 2012

Posted April 20, 2012

Monday, April 23

  • Subcontractor, Deep Foundation, will be removing the tie drill in the morning.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, April 24

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, April 25

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, April 26

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, April 27

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Deep Foundation will complete the pile and caisson drilling this week. The drill rig will be removed from the site once drilling is completed. Please check back for an update on the time and date of the drill rig removal. 

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights: L Tower & Backstage Construction April 23-27

1 The Esplanade – Construction Schedule December 19 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 19 – 23, 2011

Posted December 16, 2011

Monday, December 19

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Tuesday, December 20

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Wednesday, December 21

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Thursday, December 22

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Friday, December 23

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Saturday, December 24

Happy Holidays!

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule December 5 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 5 – 9, 2011

Posted December 2, 2011

Monday, December 5

  • Sub-contractor Deep Foundation will be installing tie backs.

Tuesday, December 6

  • Sub-contractor Deep Foundation will be installing tie backs.

Wednesday, December 7

  • Sub-contractor Deep Foundation will be installing tie backs.

Thursday, December 8

  • Sub-contractor Deep Foundation will be installing tie backs.

Friday, December 9

  • Sub-contractor Deep Foundation will be installing tie backs.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule November 28 – December 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 28 – December 2, 2011

Posted November 25, 2011

Monday, November 28

  • Sub-contractor Deep Foundation will be installing tie backs.

Tuesday, November 29

  • Sub-contractor Deep Foundation will be installing tie backs.

Wedensday, November 30

  • Sub-contractor Deep Foundation will be installing tie backs.

Thursday, December 1

  • Sub-contractor Deep Foundation will be installing tie backs.

Friday, December 2

  • Sub-contractor Deep Foundation will be installing tie backs.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade Construction Schedule November 7 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 7 – 9, 2011

Posted November 5, 2011

For example images of this work please click here.

Monday, November 7

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Tuesday, November 8

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Wednesday, November 9

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
NOTES:
  • Bulk excavating should be complete at 1 The Esplanade on Wednesday, November 9.  
  • Following the excavation work, sub-contractor, Deep Foundation, will start the first row tie back installation. An update on will be provided once information is available.
  • Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Construction Schedule for 1 The Esplanade October 24 – 28

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of October 24 – 28, 2011

Posted October 24, 2011

Monday, October 24

  • No activity is scheduled for Monday at 1 The Esplanade.

Tuesday, October 25

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street. 

Wednesday, October 26

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

Thursday, October 27

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
Friday, October 28
  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.