Backstage Construction Schedule – May 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 21 – 24, 2013

Please click here for general information on concrete pours.

Posted May 17

Monday, May 20 – Victoria Day Holiday

Tuesday, May 21

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 22

  • There will be a rebar delivery at 7:00 am.
  • The third concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Thursday, May 23

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, May 24

  • There will be a rebar delivery at 7:00 am.
  • The fourth concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 20-24-2013

Backstage Construction Schedule – May 13 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 13 – 17, 2013

Please click here for general information on concrete pours.

Posted May 10

Monday, May 13

  • The sixth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 8:30 am and concrete finishing should be completed no later than 9:30 pm.
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, May 14

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 15

  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, May 16

  • The first concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:30 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, May 17

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 13-17-2013

Backstage Construction Schedule – May 6 – 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 6 – 10, 2013

Please click here for general information on concrete pours.

Posted May 3

Monday, May 6

  • The concrete pour for the garage ramp slab, by subcontractor Italform.The pour is scheduled to begin at 10:30 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Tuesday, May 7

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 8

  • The sixth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 10:30 am and concrete finishing should be completed no later than 9:30 pm.
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Thursday, May 9

  • A 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 10

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 6-10-2013

Updated – Backstage Construction Schedule – May 2 – 3

This is the updated construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 2 to May 3, 2013

Please click here for general information on concrete pours.

UPDATED MAY 1

Thursday, May 2

  • RESCHEDULED from Tuesday April 30 to today:
    The fifth concrete pour for parking level 5, by subcontractor Italform.
    The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • UPDATED: A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 3

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryUPDATED Backstage & L Tower Construction Summary May 2-3-2013

Backstage Construction Schedule – April 29 – May 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 29 – May 3, 2013

Please click here for general information on concrete pours.

UPDATED MAY 1

Monday, April 29

  • A slab concrete pour on grade, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.

Tuesday, April 30

  • There will be a rebar delivery at 7:00 am.
  • CANCELLED & RESCHEDULED to May 2– The fifth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.

Wednesday, May 1

  • A slab concrete pour on grade, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, May 2

  • RESCHEDULED from Tuesday to today: The fifth concrete pour for parking level 5, by subcontractor Italform.
    The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • UPDATED: A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 3

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary April 29-May 3-2013

Backstage Construction Update for April 26

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  April 26, 2013

Please click here for general information on concrete pours.

Updated April 25, 2013

Friday, April 26

  • The fourth concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 9:00 am and should be completed as early as 9:00 pm but no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
  • The rebar delivery originally scheduled for 7:00 am has been rescheduled to Monday April 29.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – April 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 22 – 26, 2013

Please click here for general information on concrete pours.

Updated April 25, 2013

Monday, April 22

  • The third concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed no later than 10:30 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Tuesday, April 23

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Wednesday, April 24

  • The fourth concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed no later than 10:30 pm..
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Thursday, April 25

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, April 26

  • The fourth concrete pour for parking level 5 by subcontractor ItalformThe pour is scheduled to begin at 9:00 am and should be completed as early as 9:00 pm but no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary April 22-26-2013

Backstage Construction Schedule – April 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 15 – 19, 2013

Please click here for general information on concrete pours.

Posted April 12, 2013

Monday, April 15

  • There will be a rebar delivery at 7:00 am.
  • A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed  by 10:30 pm.

Tuesday, April 16

  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.

Wednesday, April 17

  • There will be a rebar delivery at 7:00 am.
  •  A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed by 8:30 pm.

Thursday, April 11

  • A concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed  by 10:30 pm.

Friday, April 12

  • There will be a rebar delivery at 7:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary:

Backstage Construction Schedule – April 8 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 8 – 12, 2013

Posted April 5, 2013

Monday, April 8

  • Dominus will receive gravel for the slab on the lowest grade base. One dump truck will be working throughout the day approximately 8  loads of  gravel.
  • There will be a rebar delivery at 11:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Tuesday, April 9

  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Wednesday, April 10

  • There will be a rebar delivery at 11:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Thursday, April 11

  • A parking level pour by subcontractor Italform, 80 meters of concrete starting at 9:30am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Friday, April 12

  • There will be a rebar delivery at 7:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 8-12-2013

Backstage Construction Schedule – April 1 – 5, 2013 – Updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 1 65, 2013

Updated April 3 –  2013

Monday, April 1

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Tuesday, April 2

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Wednesday, April 3 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will extend to at least  8:30 pm this evening.

Thursday, April 4 

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions.

Friday, April 5

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour may extend later than 7:00 pm, subject to weather conditions. 

Saturday, April 6 – Daytime Vehicular Road Closure – click here for details

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.