Backstage Construction UPDATE – June 20 – 21

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 20 – 21, 2013

Please click here for general information on concrete pours.

Updated June 19.

Thursday, June 20

  • Concrete pour #4 for parking level 3, by subcontractor ItalformThe pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Friday, June 21

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction UPDATE June 20-21-2013

Backstage Construction Schedule – June 15 – 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 15 – 21, 2013

Please click here for general information on concrete pours.

Updated June 14.

Saturday, June 15

  • General clean up on the site by Domninus and Italform. 

Monday, June 17

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, June 18

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #3 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, June 19

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, June 20

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, June 21

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #4 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 15-21-2013

Backstage Construction Update for June 11

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  June 11, 2013

Please click here for general information on concrete pours.

Posted June 10.

Tuesday, June 11

  • There will be a rebar delivery at 7:00 am.
  • The Parking Level 3 concrete pour originally scheduled for Monday June 10 was cancelled due to rain and has been rescheduled to today —— Concrete pour #1 for parking level 3, by subcontractor Italform. The pour is now scheduled to begin at 9:30 am and concrete finishing should be completed no later than 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – June 8 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 8 – 14, 2013

Please click here for general information on concrete pours.

Updated June 10.

Saturday, June 8

  • Cleaning concrete out from the L Tower Parking access tunnel. 

Monday, June 10

  • CANCELLED due to rain — Concrete pour #1 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, June 11

  • There will be a rebar delivery at 7:00 am.
  • Rescheduled from Monday – Concrete pour #1 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 9:30 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, June 12

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Thursday, June 13

  • Concrete pour #2 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, June 14

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 8-14-2013

Backstage Construction Schedule – June 3 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May June 3 – 7, 2013

Please click here for general information on concrete pours.

Posted May 31

Monday, June 3

  • Concrete pour #6 for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Tuesday, June 4

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Wednesday, June 5

  • Concrete pour #7 for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Thursday, June 6

  • Concrete pour #6 – part 2, for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, June 7

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 3-7-2013

Backstage Construction Schedule – May 27 – May 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 28 – June 1, 2013

Please click here for general information on concrete pours.

Posted May 24

Monday, May 27

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, May 28

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 29

  • There will be a rebar delivery at 7:00 am.
  • The fourth concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, May 30

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, May 31

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary May 27-June 1-2013

Backstage Construction Schedule – May 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 21 – 24, 2013

Please click here for general information on concrete pours.

Posted May 17

Monday, May 20 – Victoria Day Holiday

Tuesday, May 21

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 22

  • There will be a rebar delivery at 7:00 am.
  • The third concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Thursday, May 23

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, May 24

  • There will be a rebar delivery at 7:00 am.
  • The fourth concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 20-24-2013

Backstage Construction Schedule – May 13 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 13 – 17, 2013

Please click here for general information on concrete pours.

Posted May 10

Monday, May 13

  • The sixth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 8:30 am and concrete finishing should be completed no later than 9:30 pm.
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, May 14

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 15

  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, May 16

  • The first concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:30 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, May 17

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 13-17-2013

Backstage Construction Schedule – May 6 – 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 6 – 10, 2013

Please click here for general information on concrete pours.

Posted May 3

Monday, May 6

  • The concrete pour for the garage ramp slab, by subcontractor Italform.The pour is scheduled to begin at 10:30 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Tuesday, May 7

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 8

  • The sixth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 10:30 am and concrete finishing should be completed no later than 9:30 pm.
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Thursday, May 9

  • A 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 10

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 6-10-2013

Updated – Backstage Construction Schedule – May 2 – 3

This is the updated construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 2 to May 3, 2013

Please click here for general information on concrete pours.

UPDATED MAY 1

Thursday, May 2

  • RESCHEDULED from Tuesday April 30 to today:
    The fifth concrete pour for parking level 5, by subcontractor Italform.
    The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • UPDATED: A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 3

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryUPDATED Backstage & L Tower Construction Summary May 2-3-2013