L Tower Construction Schedule May 28 – June 1

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  28 – June 1, 2012

Posted May 25, 2012

NOTE:

  1. The L Tower is scheduled to reach 43 floors this week.
  2. We have been advised that The Sony Centre has an event on May 31. TV trucks may be parked adjacent to the Stage Door area on Scott Street. Traffic may be affected.

Monday, May 28 

  • A 92M (part 1) wall and column concrete pour, levels 42 – 43, starting at Noon, which is not expected to extend beyond 7:00 pm.

Tuesday, May 29

  • A 96M (part 2) wall and column concrete pour, levels 41 – 42, starting at Noon, which is not expected to extend beyond 7:00 pm.

Wednesday, May 30

Thursday, May 31

  • A 215M slab concrete pour, levels 43, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, June 1

  • A 92M (part 1) wall and column concrete pour, levels 43 – 44, starting at Noon, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 28 – June 1 summary highlights: L Tower & Backstage Construction May 28 – June 1

Backstage Construction Schedule – May 28 – June 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 28 – June 1, 2012

Posted May 25, 2012

NOTE: We have been advised that The Sony Centre has an event on May 31. TV trucks may be parked adjacent to the Stage Door area on Scott Street. Traffic may be affected.

Monday, May 28 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

Tuesday, May 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill.

Wednesday, May 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

Thursday, May 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill.

Friday, June 1

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 28 – June 1 summary highlights: L Tower & Backstage Construction May 28 – June 1

L Tower Construction Schedule May 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  22 – 26, 2012

Posted May 18, 2012

Note: The L Tower is scheduled to reach 42 floors this week.

Monday, May 21 – Victoria Day Holiday 

Tuesday, May 22

  • Heat Pump delivery starting at 7:30 am, with the estimated completion of the delivery at 11:00 am. 
    • Please note there may be some short-term disruptions to eastbound vehicular traffic.
    • Pedestrian traffic will remain open.
  • A 92M (part 1) wall and column concrete pour, levels 41 – 42 starting at Noon, which is not expected to extend beyond 7:00 pm.

Wednesday, May 23

  • A 96M (part 2) wall and column concrete pour, levels 41 – 42 starting at Noon, which is not expected to extend beyond 7:00 pm.

Thursday, May 24

Friday, May 25

  • A 215M slab concrete pour, level 42, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Saturday, May 26

  • Hoist maintenance will commence at 9:00 am and the estimated completion time for this work is 1:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 22 – 26 summary highlights: L Tower & Backstage Construction May 22 – 26

Backstage Construction Schedule – May 22 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 22 – 25, 2012

Posted May 18, 2012

Monday, May 21 – Victoria Day Holiday

PLEASE NOTE: Subcontractor Deep Foundation may be floating in a tie-back drill using a large semi-trailer, on Thursday May 24. Please check back for updates. 

Tuesday, May 22

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

Wednesday, May 23

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

Thursday, May 24

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

Friday, May 25

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 22 – 26 summary highlights: L Tower & Backstage Construction May 22 – 26

L Tower Construction Schedule May 12 – 18

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  12 – 18, 2012

Posted May 11, 2012

Note: The L Tower is scheduled to reach 41 floors this week.

Saturday, May 12

  • A floating 12M slab concrete pour, at level 4, starting 9:30 am, which is not expected to extend beyond 7:00 pm.

Monday, May 14

  • A 210M slab concrete pour, level 40, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, May 15

  • Rebar (steel) delivery starting at 12:30 pm.
  • A 101M (part 1) wall and column concrete pour, levels 40 – 41 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, May 16

  • Rebar (steel) delivery starting at 7:00 am
    • Minor disruptions to vehicular traffic may be expected. 
  • Rebar (steel) delivery starting at 12:30 pm.
  • A 101M (part 2) wall and column concrete pour, levels 40 – 41, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 17

  • The hoist will be climbed (raised) six floors (rescheduled from last week). 

Friday, May 18

  • A 220M slab concrete pour, level 41, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 12 – 18 summary highlights: L Tower & Backstage Construction May 12 – 18

Backstage Construction Schedule – May 14 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 14 – 18, 2012

Posted May 11, 2012

Monday, May 14

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker. 

Tuesday, May 15

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

Wednesday, May 16

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

Thursday, May 17

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

Friday, May 18

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

* * *

NOTES:

All the piles and caissons are complete on the site.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 12 – 18 summary highlights: L Tower & Backstage Construction May 12 – 18

L Tower Construction Schedule May 7 – 11

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  7 – 11, 2012

Posted May 4, 2012

Note: The L Tower is scheduled to reach 40 floors this week.

Monday, May 7

  • A 190M slab concrete pour, level 39, starting 10:00 am,, which is not expected to extend beyond 7:00 pm.

Tuesday, May 8

  • A 99M (part 1) wall and column concrete pour, levels 39 – 40 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • The hoist will be raised three (3) floors, to stop at level 33.

Wednesday, May 9

  • Rebar (steel) delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 39 – 40, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 10

Friday, May 11

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 4 – 7 summary highlights: L Tower & Backstage Construction May 7 – 11

Backstage Construction Schedule – May 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for May 7 – 11, 2012

Posted May 04, 2012

Monday, May 7

  • Between 9 am and 3 pm, Deep Foundation, will be “float out” the drill rig from the site at 1 The Esplanade on a large truck, under police escort.
    • Pedestrian and vehicular traffic will be impacted during this operation. 
    • Please check back on May 7 for a more precise time for the “float out.”
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 8

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 9

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 10

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

All the piles and caissons are complete on the site.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 7 – 11 summary highlights: L Tower & Backstage Construction May 7 – 11

L Tower Construction Schedule April 30 – May 4

This is the current construction schedule for 8 The Esplanade – L Tower – for April 30 – May 4, 2012

Posted April 27, 2012

Note: The L Tower is scheduled to reach 39 floors this week.

Monday, April 30

  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am,, which is not expected to extend beyond 7:00 pm.

Tuesday, May 1

  • A 99M (part 1) wall and column concrete pour, levels 38 – 39 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, May 2

  • Rebar delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 38 – 39, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 3

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, May 4

  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 39, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

Backstage Construction Schedule – April 30 – May 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for April 30 – May 4, 2012

Posted April 27/12

Monday, April 30

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 1

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 2

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 3

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 4

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4