L Tower Construction Schedule August 18 – 24
August 17, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for August 18th to 24th
Posted August 17, 2012
Saturday, August 18
- There will be a crane mast extension.
Monday, August 20
- A rebar (steel) delivery starting at 7:00AM and 12:30PM.
Tuesday, August 21
- A rebar (steel) delivery starting at 10:00 am.
- A 215M (cubic metre) slab concrete pour at level 56, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
Wednesday, August 22
- A 96M (cubic metre) part one (1), wall and column concrete pour, levels 56 – 57, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.
Thursday, August 23
- A 92M (cubic metre) part 2, wall and column concrete pour, levels 56 – 57, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.
- There will be a rebar (steel) delivery starting at 12:30 pm.
Friday, August 24
- A rebar (steel) delivery starting at 7:00AM and 12:30PM
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24