Backstage Construction Schedule – August 4 – August 10
August 3, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for August 4 – August 10, 2012
Updated August 3, 2012
- The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect.
- A shuttle bus service will be provided during the road closure running approximately every 12 – 15 minutes from 7 am to 7 pm daily, connecting The Esplanade and Scott Street to Union Station, Bay & Front, King & Yonge and Berczy Park.
- Please click here for the route map for the shuttle bus service.
- For a PDF Copy: L Tower Community Shuttle Bus Route – MAP
Monday, August 6 – Civic Holiday
Tuesday, August 7
- Sub-contractor, C & M McNally boring the tunnel.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Wednesday, August 8
- Sub-contractor, C & M McNally boring the tunnel.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Thursday, August 9
- C & M McNally removing Tunnel Boring Machine
- There will be significant impact to The Esplanade and surrounding streets due to the setup of a 500 ton crane, support semis and 130 foot long float to take away the Tunnel Boring Machine. There will be a police escort for the float as it leaves the site.
Friday, August 10
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
NOTES:
* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: Construction Summary August 4 – August 10