L Tower – 8 The Esplanade – Construction Schedule Feb 21 – 25

This is the current construction schedule for 8 The Esplanade – L Tower for February 21 – 25, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 22

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am

Thursday, February 23

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am.
  • An 190m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, February 24

  • An 100m concrete pour scheduled to start at 2:00 pm, which might  extend beyond 7:00 pm.

Saturday, February 25

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.

Join 37 other followers