Backstage – 1 The Esplanade – Construction Schedule Feb 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 20 – 24, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 22

  • Sub-contractor, Deep Foundation disassembling drill.
  • Sub-contractor, GFL Excavating, and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, February 23

  • Sub-contractor, Deep Foundation floating out the drill rig under police escort. Time to be posted.
  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Friday, February 24

  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.

Join 37 other followers