L Tower – 8 The Esplanade – Construction Schedule Feb 21 – 25

This is the current construction schedule for 8 The Esplanade – L Tower for February 21 – 25, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 22

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am

Thursday, February 23

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am.
  • An 190m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, February 24

  • An 100m concrete pour scheduled to start at 2:00 pm, which might  extend beyond 7:00 pm.

Saturday, February 25

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage – 1 The Esplanade – Construction Schedule Feb 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 20 – 24, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 22

  • Sub-contractor, Deep Foundation disassembling drill.
  • Sub-contractor, GFL Excavating, and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, February 23

  • Sub-contractor, Deep Foundation floating out the drill rig under police escort. Time to be posted.
  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Friday, February 24

  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower from Yonge and King

L Tower from Yonge & King, February 16, 2012

Update for Backstage 1 The Esplanade for Wednesday February 15

Construction Update for 1 The Esplanade – L Tower parking and Backstage condominium for Wednesday February 15, 2012

Posted February 15, 2012

Update:

  • Sub-contractor, GFL Excavating will have dump trucks removing material from the site: 4 dump trucks doing 5 rounds each..

Backstage – 1 The Esplanade – Construction Schedule Feb 13 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 13 – 17, 2012

Posted February 10, 2012

Monday, February 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 14

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Wednesday, February 15

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 16

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Friday, February 17

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower – 8 The Esplanade – Construction Schedule Feb 13 – 17

This is the current construction schedule for 8 The Esplanade – L Tower for February 13 – 17, 2012

Posted February 10, 2012

Monday, February 13

  • A steel delivery at 10:00 am.
  • An 100m concrete pour scheduled to start at 2:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, February 14

  • A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 15

  • A steel delivery at 7:00 am.
  • A second steel delivery at 10:00 am.

Thursday, February 16

  • A steel delivery at 7:00 am.
  • A second steel delivery at 10:00 am.
  • An 180m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, February 17

  • An 180m concrete pour scheduled to start at 2:00 pm, which may extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Update: Backstage – 1 The Esplanade – Construction Schedule Feb 9 – 10

Construction Update for 1 The Esplanade – L Tower parking and Backstage condominium for February 9  & 10, 2012

Posted February 8, 2012

Thursday, February 9

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

Friday, February 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower – 8 The Esplanade – Construction Schedule Feb 4 – 10

This is the current construction schedule for 8 The Esplanade – L Tower for February 4 – 10, 2012

Posted February 3, 2012

UPDATE: Saturday, February 4

  • On-going infrastructure installation for Bell (telephone), trenching through site.

Monday, February 6

  • On-going infrastructure installation for Bell (telephone), trenching through site, and north on Yonge Street.
  • Concrete pour scheduled to start at 11:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, February 7

  • Window delivery at 7:30 am.
  • Concrete pour scheduled to start at 2:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 8

  • Window delivery at 7:30 am.
  • Concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, February 9

  • Rebar delivery.

Friday, February 10

  • Rebar delivery.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage – 1 The Esplanade – Construction Schedule Feb 6 – 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 6 – 10, 2012

Updated February 8, 2012

Monday, February 6

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL will be delivering a backhoe.
  • Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 7

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 8

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 9

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

Friday, February 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower 24 floors and counting

image

The L Tower rising over Yonge Street as seen from the GO Transit Bus Station. February 2, 2012

Follow

Get every new post delivered to your Inbox.

Join 26 other followers